Colombia’s ISA $65 mn project in Brazil to operate earlier than planned

With an investment of US $65 million, ISA’s subsidiary CTEEP announced that its Aguapeí interconnection project in Brazil is six months ahead of schedule. The project has more than 120 km of transmission lines and two substations with 1,400 MW of power (Alta Paulista and Baguaçu)

Source: El Espectador